Dispatching Sauter

... the SCADA-system is the only of its cost; 2) to tie a few meters network thermal and electrical accounting; 3) to get control over 2 of 6 ventilation systems; 4) control the PCS systems in the individual heating units. Node heat metering Teplosfera Sauter nova220 Sauter EY3600 It turned out that the problem is complicated by the fact that: – The customer wants to maintain existing systems and controls, as, in his words, they work perfectly, for example, two of the company SAUTER PLC placed in the ITP; – Pump control cabinet partially destroyed – removed thermal protection, so that when issues have to automatically sort out the closet with the preparation of the necessary project documentation; – Cold water supply management ...